Job statistics are not logged for those jobs that are executing at the time of the Strategy Intelligence Server shutdown. This behavior is the same for a manual shutdown or for an unexpected shutdown (crash).
Report/Document job statistics are logged into the IS_REPORT_STATS after the completion of the job. A job completion does not necessarily indicate a successful completion; it just means that a job should complete execution - either successful execution, manual cancellation of job, or job erroring out.
Consider that a report, Report A, is executing on the Strategy Intelligence Server. If the server is shutdown by the Administrator before the report completes execution, then there is no record in the IS_REPORT_STATS table corresponding to Report A's execution at that time. The result is the same even if the server shuts down unexpectedly.
If the report completes successfully or if it errors out because of some reason or if the user cancels the job, there is a record of that execution in the IS_REPORT_STATS table.
As seen in the example data below, the report starts execution at 9:42:19, and finishes execution at 9:53:31 (execution finish timestamp = 'requestrectime' + execfinishtime). However, this record for execution is written into the Statistics table only at 9:53:33 i.e. after completion of the execution, as indicated by the timestamp value in the RECORDTIME column.