SYMPTOM
After upgrading from Strategy 9.3 to 10.x, some metrics and subtotals show different results as shown below:
Strategy 9.3.1

Strategy 10.1

In the SQL view Analytical Engine calculation steps, the evaluation order is different between 9.3 and 10.1.
CAUSE
This is working as designed in Strategy Secure Enterprise 10.x. The default evaluation order has been modified in 10.x. In 10.x, the default option is as shown below: 9.x order: Calculate derived elements/consolidation before derived metric/smart compound metric, "total" subtotal as smart and other subtotals as non-smart

In 9.x, the default evaluation order is as shown below: 6.x order: Calculate derived metric/smart compound metric before derived elements/consolidation and all subtotals as smart

ACTION
If users prefer to see the results seen in 9.3.x, change the evaluation order to the first option: 6.x order: Calculate derived metric/smart compound metric before derived elements/consolidation and all subtotals as smart
To apply this at the project level, the VLDB property can be changed at the project level from project configuration > project definition > advanced > project VLDB settings 'Configure'
The Strategy Internal Reference Number for the issue discussed in this technical note is DE22961.
KB275279