In the Project Configuration Editor in Desktop, under Governing Rules -> Default -> Result Sets, administrators can specify values of Intelligence Server Elapsed Time for Scheduled reports, which is a project level governing setting, not based on users, as showed below.

However, in some situations, users may need to differentiate powerful users from normal users with different timeout values.
The following procedure describes how to set different Intelligence Server Elapsed Time for Scheduled reports for different users in Strategy Developer.


Note: The workload of duplicating projects and changing corresponding governing rules may be heavy, which is a factor to consider.